Alexandra School Extension

Design and Build project awarded under the North Wales 21C Schools programme through the North Wales Collaborative Framework for the extension to the live Primary School in Wrexham.


Contract:   NEC 3 Option C
Value:          £935,000
Duration:   28 Weeks

 

ENGAGING - Throughout the project, the site team have delivered a programme of educational engagement activities with the school pupils. This included a Health and Safety Poster competition and visit from safety mascot Ivor Goodsite.

ENHANCING VALUE - By working collaboratively to manage the budget cost plan with the client, Read's design and construct team generated salient economies within the design to deliver enhanced offerings including additional fencing, soft play and playground markings.