Ysgol Ty Ffynnon, Shotton

New build construction of a BREEAM Excellent 320 pupil entry primary school through a Partnered contract. Through an integrated team approach, Read championed the project as a BIM pilot scheme.


Contract:   PPC 2000 Partnering Contract
Value:          £6,300,000
Duration:   63 Weeks

 

AWARD WINNING - The offer to champion the project as a BIM pilot project demonstrates Read's collaborative approach, through which, a programme of workshops, case studies and lesson sharing events was developed and delivered through the scheme. The programme upskilled the client, supply chain, design partners and other main contractors. This approach formed the basis of the Constructing Excellence Wales Special Recognition Award for Innovation 2015.

LEAN CONSTRUCTION - By deploying the LEAN construction principles of "Right First Time" and sequential inspection, built in quality was delivered throughout the project. These principles, now embedded as standard operating procedures, resulted in the project being awarded LABC Regional and All Wales Best Educational Building 2015.

SOFT LANDINGS - Through a structured approach to handover, aligned with the Government Soft Landing (GSL) principles of engaging and exchanging information early and effectively, the handover and occupation of the facility has been achieved with nil disruption to the effectiveness of client operations. Our project delivery team remained assigned as the single point of contact to address ongoing requirements 6 weeks post occupation. By effectively managing the mechanical and electrical installation and ensuring fully communicated progress, early familiarisation training and ongoing support was delivered.


Results

Developing and building on long term relationships with repeat clients fosters an ethos of collaboration and LEAN working. Read have practiced the principles of collaborative and partnering for over 10 years and offer this management style to all clients on all projects. This long term relationship has nurtured an ongoing relationship to build on these principles to deliver mutually beneficial outcomes. By working in this way, Read presented the benefits to Constructing Excellence Wales and were awarded a Special Recognition Award, together with the project being flagged as an exemplar of best practice. 



EXCELLENT

BREEAM rating

11 EVENTS

Promoting the industry

89%

Waste diverted from landfill

34nr

Trainees & Apprentices

65%

Local labour

EXEMPLAR

CEW Exemplar project



Ysgol Ty Ffynnon, Shotton

Achievements

  • CC Performance Beyond Compliance
  • LABC Cymru All Wales Building Excellence Award 2015
  • LABC Regional Excellence Award 2015
  • CEW Exemplar Case Study
  • CEW Innovation Special Recognition Award

 





Back to School - Live Online

March 6th 20141/3

Wales is full of great construction projects, but most of the ones we highlight have been completed and assessed – rarely do we report on a live scheme that you can watch day by day and sometimes even hour by...


Read full story

Shotton Primary School Press Release

March 21st 20132/3

Shotton Primary School Press Release Supported by Read Construction and Lovelock Mitchell, Flintshire County Council (FCC) is leading the way in Wales by embracing the BIM method of building design and operational management. Building Information Modelling (BIM) has increasingly become...


Read full story

Performance Beyond Compliance

August 25th 20103/3

In recognition of Construction Excellence, Read has been awarded a Performance Beyond Compliance certificate for the Ward 52 Refurbishment at Arrowe Park Hospital, along with Site Manager Steve Day. “This really is at the shiny end of contract delivery, directly...


Read full story