Design and Construction of a factory extension within a tight site adjacent to dense residential area. The project was managed to ensure zero operational downtime for the clients' manufacturing operations.


Contract:   JCT Design & Build
Value:          £1,000,000
Duration:   21 Weeks

 

ZERO DOWNTIME - With shared access and a tight development site area, a key concern for the client of this manufacturing facility was the impact of the construction activities on the ongoing operational effectiveness of the factory. Daily liaison and weekly programming meetings with Read's site team ensured that construction activities and resource plans were shared with the client team with all deliveries and logistics planned around the client activities.

ACCOMMODATING - Delivered on budget, the client instructed an additional package of works to over clad the existing factory roof with the specification of composite roofing solution proposed by Read demonstrating improved insulation, extended life and low maintenance.